Physical Progress as of 31st August, 2022

Contract Packages Cumulative progress (%) as of a previous month Cumulative progress (%) as of 31.08.2022

 

MC-1 (including Hydro-Mechanical works) 69.87 69.87
MC-2 (including Hydro-Mechanical works) 100 100
MC-3 (including Hydro-Mechanical works) 99.36 99.41
Electro-Mechanical works 97.61 97.69
Transmission Line 99.94 99.94
Total 87.49 87.51