INFRASTRUCTURE
Local Contractors involved in Civil Infrastructure works as of 30th April 2026:
Total No. of Local Contractors, (Work Completed): 110
Total No. of Local Contractors, (On-going Works): 2
Total No. of Local Contractors: 112
Total No. of Residential Buildings: 108
Total No. of Residential Units: 522 units
| Sl.No. | Name of Packages | Detail of the Work | Remarks |
| A | K- Buildings – Permanent Residential Buildings. | ||
| 1 | Package#1 (102 Units) | Construction of H-type (6 Units x 17 Blocks) for Permanent colony of Punatsangchhu – I H.E. Project at Bjimthangkha(Package-1) | Completed |
| 2 | Package#2 (60 Units) | Construction of H-Type Buildings (6 Units x 10 Blocks) for permanent colony of Punatsangchhu – I H.E. Project at Bjimthangkha (Package-2) | Completed |
| 3 | Package#3 ( 66 Units) | Construction of H-Type Buildings (6 Units x 11 Blocks) for permanent colony of Punatsangchhu – I H.E. Project at Bjimthangkha (Package-3) | Completed |
| 4 | Package#4 (78 Units) | Construction of G-Type Buildings (6 Units x 13 Blocks) for permanent colony of Punatsangchhu – I H.E. Project at Bjimthangkha (Package -4) | Completed |
| 5 | Package#5 (78 Units) | Construction of G-Type Buildings (6 Units x 13 Blocks) for permanent colony of Punatsangchhu – I H.E. Project at Bjimthangkha (Package-5) | Completed |
| 6 | Package#6 (48 Units) | Construction of F-Type Buildings (4 Units x 12 Blocks) for permanent colony of Punatsangchhu – I H.E. Project at Bjimthangkha (Package-6) | Completed |
| 7 | Package#7 (60 Units) | Construction of E-Type Buildings (4 Units x 15 Blocks) for permanent colony of Punatsangchhu-I H.E. Project at Bjimthangkha (Package-7) | Completed |
| 8 | Package#8 (30 Units) | Construction of A, B, C & D -Type Buildings (Total 30 Units) including site development and internal roads for permanent colony of PHPA-I at Bjimthangkha (Package-8). | Completed |
| 9 | Package#A (69 Units) | Construction of Residential Complex for 40 Bedded Hospital Comprising of C, D, E,F,G & H-Type Buildings (Total 69 Units) including winding/Construction of internal colony roads at Jatshokha, Wangdue. | Completed |
| 10 | Construction of Police Station & Residential quarter under construction in PHEP-II shared with PHEP-I. (Residential building) | Completed | |
| B | K- Buildings – Non-Permanent Residential Buildings. | ||
| 1 | Construction of Mechanical workshop and Central stores at Hebesa. | Completed | |
| 2 | Construction of Testing laboratory building at Hebesa. | Completed | |
| 3 | Extension works for Bajo BHU | Completed | |
| 4 | Const. of Six Classroom building for Lobesa LSS | Completed | |
| 5 | Construction of 7 Nos. Stores for Testing Equipment’s & Samples at Batching Plant Sites of PHPA | Completed | |
| 6 | Construction of 100 MT additional Magazine at Hebesa | Completed | |
| 7 | Site development, improvement of rooms, water supply & Construction of Toilets for Bajo BHU. | Completed | |
| 8 | Construction of Pharmacy store & general Store for Bajo Hospital | Completed | |
| 9 | Construction of Multiple Fire Tenders Garage Cum Office Cum Storeroom at Hebesa. | Completed | |
| 10 | Package #9 | Construction of Office, Executive & Field Hostel Buildings including Road works in PHPA-I colony at Bjimthangkha (Package-9). | Completed |
| 11 | Package #11 | Construction of Auditorium in PHPA-I colony at Bjimthangkha (Pkg.11). | Completed |
| 12 | Package #10 A | Miscellaneous Building, BHU-Gr.-II, Telephone Exchange & Bank, Police Station / Fire Station, Bus Stand& Public Utilities, Marketing complex, Security Check Post, & amphitheater) Package-10A. | Completed |
| 13 | Package #10 B | Construction of primary school building of PHPA-I including site development & road works at Bjimthangkha (Pkg.10 B). | Completed |
| 14 | Package #B | Construction of 40 Bedded Hospital at Jatshokha | Completed |
| 15 | Construction of additional 12 classroom building & ADM building with conference hall in the premises of Bajo HSS including site development works. | Completed | |
| 16 | Construction of Explosive Magazine building of capacity 50 MT including construction of approach road. | Completed | |
| 17 | Construction of Police Station & Residential quarter under construction in PHEP-II shared with PHEP-I (Non- Residential). | Completed | |
| 18 | Package #10 D | Construction of Lhakhang in PHPA-I colony at Bjimthangkha (Pkg.10D). | Upcoming works |
| 19 | Package #10 C | Construction of Club building in PHPA-I colony at Bjimthangkha (Pkg.-10C). | Completed |
| 20 | Construction of office building at dam site | Completed | |
| 21 | Old Transit Camp and office building purchased from THPA. | Completed | |
| 22 | Construction of Office cum store/Record Room Building at p’ling | Completed | |
| 23 | Purchase of houses from DGPC at Basochu | Completed | |
| 24 | Namgyel Khangzang Chorten | Construction of Religious Stupa (Local Name: Namgyel Khangzang Chorten) at Dam Site | Completed |
| 25 | Entry Gates | Entry Gates and boundary wall, MS Gates in PHPA-I colony at Bjimthangkha | Completed |
| 26 | Store/Shed | Construction of Temporary Shed or Store at Bjimthangkha | Completed |
| C | Other Miscellaneous works under K- Buildings Head | ||
| 1 | Colony Roads | Construction of Approach Road for the PHPA Colony at Bjimthangkha bifurcating from substation road RD 0.00km to RD 1.47km near PHPA Damsite | Completed |
| 2 | Colony Roads | Construction of Approach Road for the PHPA Colony at Bjimthangkha from RD 1.47km to RD 2.57km near PHPA Damsite | Completed |
| 3 | Miscellaneous works | Development of Assembly ground at Lobesa Lower Secondary School | Completed |
| 4 | Miscellaneous works | Construction of Catch Water Drain above the Approach Road to PHPA-I Colony near Dam site | Completed |
| 5 | Miscellaneous works | Extension of Catch water drain above the Approach Road to PHPA-I Colony near Dam site | Completed |
| 6 | Miscellaneous works | Construction of Fencing for Project Plantation Area at Wolakha | Completed |
| 7 | Miscellaneous works | Site development, approach road and parking, compound fencing & gate at Hebesa. | Completed |
| 8 | Miscellaneous works | Construction of partition work & reinstallation of Air Conditioners in proposed new conference hall at Lobesa. | Completed |
| 9 | Miscellaneous works | Protection works of slide zone near Cable Car Bench & Approach Road to Project Colony near dam site area. | Completed |
| 10 | Miscellaneous works | Site levelling of substituted land allotted to immediately affected households due to construction of coffer dam. | Completed |
| 11 | Miscellaneous works | Repair, Rehabilitation & reconstruction of catch water drain above PHPA-I Colony | Completed |
| 12 | Miscellaneous works | Construction of Assembly ground at Bajo HSS. | Completed |
| D | O-Miscellaneous works | ||
| 1 | WTP | Construction of water treatment plant including its approach road in PHPA Colony near Dam complex at Bjimthangkha, Wangdue. | Completed |
| 2 | WTP | Construction of water treatment plant including its approach road for residential complex of 40 bedded hospital & for 40 bedded hospitals at Jatshokha, Wangdue. | Completed |
| 3 | Water supply line | Laying of pipeline for drinking water supply & other ancillary works from intake near Nahi School to Project colony at Bjimthangkha, Wangdue. | Completed |
| 4 | Water supply line | Laying of pipeline for drinking water supply 4km upstream of Nahi School to new intake site. | Completed |
| 5 | Water supply line | Construction of Raw water scheme for drinking water supply Scheme for Residential & Hospital complex at Jatshokha. | Completed |
| 6 | Water supply line | Construction of infrastructure service i.e., External water supply, Sewerage, horticulture & drainage works of project colony at Bjimthangkha. | Completed |
| 7 | Water supply line | Construction of infrastructure service i.e., External water supply, Sewerage, horticulture & drainage works of Residential complex of 40beded hospital & for hospital complex at Jatshokha. | Completed |
| 8 | STP | Construction of Sewerage Treatment Plant to PHPA-I colony at Bjimthangkha. | Completed |
| 9 | STP | Construction of Sewerage Treatment Plant to PHPA-I colony at Jatshokha. | Completed |
| 10 | Park & Services | Construction of children park & welfare centers for officials/labours & Landscaping of colony. | Completed |
| 11 | Maintenance & Service: | R&M of Water Supply facilities for various colonies. | Completed |
| 12 | Maintenance & Service: | R&M of Sanitation & drainage facilities of various colonies. | Completed |
| 13 | Maintenance & Service: | R&M of hospitals (including PHC) | Completed |
| 14 | Maintenance & Service: | Maintenance of Parks, welfare centers, clubs, Lhakhang, auditorium and school. | Completed |
| 15 | Maintenance & Service: | R&M of Rest House and Field Hostels | Completed |
| 16 | Maintenance & Service: | R&M of Research and Quality Control Lab/ Construction material testing and establishment of soil and rock testing laboratory | Completed |
| 17 | Maintenance & Service: | R&M of Colony. | On-going works |
| 18 | Maintenance & Service: | Construction of Crate wall near Dam Sub Station and Repair/Maintenance of Storm Water Drains in PHPA-I Colony. (M/s RMA Construction) | On-going works |
| E | R-Communication works | ||
| 1 | Road Improvement Works | Construction of Re-aligned National Highway bifurcating at 1.78 Km from Wangdue Bridge for a Stretch of 800m upto the proposed Hesothangkha Bridge at Hesothangkha, Wangdue Phodrang | Completed |
| 2 | Road Improvement Works | Construction of Re-aligned National Highway bifurcating at 1.78km from Wangdue Bridge for a stretch of 850m from RD 830m to RD 1680m | Completed |
| 3 | Road Improvement Works | Construction of Re-aligned National Highway bifurcating at 1.78km from Wandgdue Bridge for a stretch of 1000m from RD 1680m to RD 2680 | Completed |
| 4 | Road Improvement Works | Construction of Re-aligned National Highway bifurcating at 1.78km from Wangdue Bridge for a stretch of 1100m from RD 2680m to RD 3780m | Completed |
| 5 | Road Improvement Works | Construction of Re-aligned National Highway bifurcating at 1.78km from Wangdue Bridge for a stretch of 1045m from RD 3780m to RD 4825m | Completed |
| 6 | Road Improvement Works | Strengthening (Restoration and slope protection works of affected reaches of realigned Wangdue Tsirang National Highway | Completed |
| 7 | Road Improvement Works | Construction of Re-aligned National Highway Bifurcating at 1.78 Km from Rd 3780 Km SH. Construction of Catch Water Drain above National Highway at RD 3940m. | Completed |
| 8 | Road Improvement Works | Improvement of Approach Road & Parking Area for PHPA Head Office at Thimphu. | Completed |
| 9 | Road Improvement Works | Improvement of Primary National Highway (Metsina Wangdue Zam till 19 Km. towards Sungkosh) | Completed |
| 10 | Road Improvement Works | Repair of damaged portion of National Highway from RD 1.78 Km.to RD 7.00 Km. on Wangdue Tsirang highway. | Completed |
| 11 | Road Improvement Works | Improvement of Wangdue-Tsirang Primary National Highway and Wangdue Nobding National Highway. | Completed |
| 12 | Road Improvement Works | Widening of the Wangdue- Tsirang National Highway from Wangdue to Taksha and widening of the Wangdue-Trongsa National Highway till Nobding. | Completed |
| 13 | Road Improvement Works | Widening of Road between Tanalum & Tshimasham on Phuntsholing- Thimphu Highway. | Completed |
| 14 | Bridge Works | Strengthening of Bridges at Damchhu & Simthokha on P/Ling-Thimphu Highway. | Completed |
| 15 | Bridge Works | Improvement of curves at Semtokha fly over. | Completed |
| 16 | Bridge Works | Rehabilitation & Up- gradation of Damchhu & Semtokha Bridge on Phuentsholing- Thimphu highway. | Completed |
| 17 | Improvement Road Works | Regrading of road at Semtokha bridge on Phuentsholing – Thimphu highway. | Completed |
| 18 | Improvement Road Works | Resurfacing & Strengthening of National Highway from Thimphu to Wangdue. | Completed |
| 19 | Improvement Road Works | Construction of Approach Road to STP for PHPA-I Colony. | Completed |
| 20 | Bridge Works | Construction of three nos of bridges to be replaced beyond Gedu to Project site. | Completed |
| 21 | Bridge Works | Design, Fabrication, Transportation, Errection & construction of Steel Truss Bridge (Deck Type) on Hesothangkha stream on the proposed Realigned Wangdue Tsirang National highway at Hesothangkha. | Completed |
| 22 | R&M works | R&M of Road & Bridge works | Upcoming works |
| 23 | New Road Works | Construction of 310m Re-aligned NH from Bjimthangkha BHU towards STP Area. (M/s Nayeab Construction) | On-going works |
| 24 | Widening Works | Widening & Pavement works of Existing Colony from Dam takeoff Jn. to BHU. | Upcoming works |
| 25 | Widening Works | Widening & Blacktopping of Temporary NH Road from BHU to STP PNH Jn. | Upcoming works |
| 26 | Widening Works | Construction of Temporary NH Way from Gaselo Junction to Bjimthangkha BHU. (5 packages) | Upcoming works |
| F | P-Maintenance works | ||
| 1 | Building & Other Components | Maintenance of K-Buildings (@ 1% of K-Buildings) | On-going works |
| 2 | Building & Other Components | Maintenance of Wangdue-Tsirang Primary National Highway from RD. 9.5 km to RD 20.5 km and maintenance of Hesothangkha Bypass Road on Wangdue-Tsirang Highway from RD 1.74 km to RD 6.5 km | Completed |