INFRASTRUCTURE

Local Contractors involved in Civil Infrastructure works as of 30th April 2026:

Total No. of Local Contractors, (Work Completed): 110

Total No. of Local Contractors, (On-going Works): 2

Total No. of Local Contractors: 112

Total No. of Residential Buildings: 108

Total No. of Residential Units: 522 units

Sl.No. Name of Packages Detail of the Work Remarks
A K- Buildings – Permanent Residential Buildings.  
1 Package#1 (102 Units) Construction of H-type (6 Units x 17 Blocks) for Permanent colony of Punatsangchhu – I H.E. Project at Bjimthangkha(Package-1) Completed
2 Package#2 (60 Units) Construction of H-Type Buildings (6 Units x 10 Blocks) for permanent colony of Punatsangchhu – I H.E. Project at Bjimthangkha (Package-2) Completed
3 Package#3 ( 66 Units) Construction of H-Type Buildings (6 Units x 11 Blocks) for permanent colony of Punatsangchhu – I H.E. Project at Bjimthangkha (Package-3) Completed
4 Package#4 (78 Units) Construction of G-Type Buildings (6 Units x 13 Blocks) for permanent colony of Punatsangchhu – I H.E. Project at Bjimthangkha (Package -4) Completed
5 Package#5 (78 Units) Construction of G-Type Buildings (6 Units x 13 Blocks) for permanent colony of Punatsangchhu – I H.E. Project at Bjimthangkha (Package-5) Completed
6 Package#6 (48 Units) Construction of F-Type Buildings (4 Units x 12 Blocks) for permanent colony of Punatsangchhu – I H.E. Project at Bjimthangkha (Package-6) Completed
7 Package#7 (60 Units) Construction of E-Type Buildings (4 Units x 15 Blocks) for permanent colony of Punatsangchhu-I H.E. Project at Bjimthangkha (Package-7) Completed
8 Package#8 (30 Units) Construction of A, B, C & D -Type Buildings (Total 30 Units) including site development and internal roads for permanent colony of PHPA-I at Bjimthangkha (Package-8). Completed
9 Package#A (69 Units) Construction of Residential Complex for 40 Bedded Hospital Comprising of C, D, E,F,G & H-Type Buildings (Total 69 Units) including winding/Construction of internal colony roads at Jatshokha, Wangdue. Completed
10 Construction of Police Station & Residential quarter under construction in PHEP-II shared with PHEP-I. (Residential building) Completed
B K- Buildings – Non-Permanent Residential Buildings.
1 Construction of Mechanical workshop and Central stores at Hebesa. Completed
2 Construction of Testing laboratory building at Hebesa. Completed
3 Extension works for Bajo BHU Completed
4 Const. of Six Classroom building for Lobesa LSS Completed
5 Construction of 7 Nos. Stores for Testing Equipment’s & Samples at Batching Plant Sites of PHPA Completed
6 Construction of 100 MT additional Magazine at Hebesa Completed
7 Site development, improvement of rooms, water supply & Construction of Toilets for Bajo BHU. Completed
8 Construction of Pharmacy store & general Store for Bajo Hospital Completed
9 Construction of Multiple Fire Tenders Garage Cum Office Cum Storeroom at Hebesa. Completed
10 Package #9 Construction of Office, Executive & Field Hostel Buildings including Road works in PHPA-I colony at Bjimthangkha (Package-9). Completed
11 Package #11 Construction of Auditorium in PHPA-I colony at Bjimthangkha (Pkg.11). Completed
12 Package #10 A Miscellaneous Building, BHU-Gr.-II, Telephone Exchange & Bank, Police Station / Fire Station, Bus Stand& Public Utilities, Marketing complex, Security Check Post, & amphitheater) Package-10A. Completed
13 Package #10 B Construction of primary school building of PHPA-I including site development & road works at Bjimthangkha (Pkg.10 B). Completed
14 Package #B Construction of 40 Bedded Hospital at Jatshokha Completed
15 Construction of additional 12 classroom building & ADM building with conference hall in the premises of Bajo HSS including site development works. Completed
16 Construction of Explosive Magazine building of capacity 50 MT including construction of approach road. Completed
17 Construction of Police Station & Residential quarter under construction in PHEP-II shared with PHEP-I (Non- Residential). Completed
18 Package #10 D Construction of Lhakhang in PHPA-I colony at Bjimthangkha (Pkg.10D). Upcoming works
19 Package #10 C Construction of Club building in PHPA-I colony at Bjimthangkha (Pkg.-10C). Completed
20 Construction of office building at dam site Completed
21 Old Transit Camp and office building purchased from THPA. Completed
22 Construction of Office cum store/Record Room Building at p’ling Completed
23 Purchase of houses from DGPC at Basochu Completed
24 Namgyel Khangzang Chorten Construction of Religious Stupa (Local Name: Namgyel Khangzang Chorten) at Dam Site Completed
25 Entry Gates Entry Gates and boundary wall, MS Gates in PHPA-I colony at Bjimthangkha Completed
26 Store/Shed  Construction of Temporary Shed or Store at Bjimthangkha Completed
C Other Miscellaneous works under K- Buildings Head
1 Colony Roads Construction of Approach Road for the PHPA Colony at Bjimthangkha bifurcating from substation road RD 0.00km to RD 1.47km near PHPA Damsite Completed
2 Colony Roads Construction of Approach Road for the PHPA Colony at Bjimthangkha from RD 1.47km to RD 2.57km near PHPA Damsite Completed
3 Miscellaneous works Development of Assembly ground at Lobesa Lower Secondary School Completed
4 Miscellaneous works Construction of Catch Water Drain above the Approach Road to PHPA-I Colony near Dam site Completed
5 Miscellaneous works Extension of Catch water drain above the Approach Road to PHPA-I Colony near Dam site Completed
6 Miscellaneous works Construction of Fencing for Project Plantation Area at Wolakha Completed
7 Miscellaneous works Site development, approach road and parking, compound fencing & gate at Hebesa. Completed
8 Miscellaneous works Construction of partition work & reinstallation of Air Conditioners in proposed new conference hall at Lobesa. Completed
9 Miscellaneous works Protection works of slide zone near Cable Car Bench & Approach Road to Project Colony near dam site area. Completed
10 Miscellaneous works Site levelling of substituted land allotted to immediately affected households due to construction of coffer dam. Completed
11 Miscellaneous works Repair, Rehabilitation & reconstruction of catch water drain above PHPA-I Colony Completed
12 Miscellaneous works Construction of Assembly ground at Bajo HSS. Completed
D O-Miscellaneous works
1 WTP Construction of water treatment plant including its approach road in PHPA Colony near Dam complex at Bjimthangkha, Wangdue. Completed
2 WTP Construction of water treatment plant including its approach road for residential complex of 40 bedded hospital & for 40 bedded hospitals at Jatshokha, Wangdue. Completed
3 Water supply line Laying of pipeline for drinking water supply & other ancillary works from intake near Nahi School to Project colony at Bjimthangkha, Wangdue. Completed
4 Water supply line Laying of pipeline for drinking water supply 4km upstream of Nahi School to new intake site. Completed
5 Water supply line Construction of Raw water scheme for drinking water supply Scheme for Residential & Hospital complex at Jatshokha. Completed
6 Water supply line Construction of infrastructure service i.e., External water supply, Sewerage, horticulture & drainage works of project colony at Bjimthangkha. Completed
7 Water supply line Construction of infrastructure service i.e., External water supply, Sewerage, horticulture & drainage works of Residential complex of 40beded hospital & for hospital complex at Jatshokha. Completed
8 STP Construction of Sewerage Treatment Plant to PHPA-I colony at Bjimthangkha. Completed
9 STP Construction of Sewerage Treatment Plant to PHPA-I colony at Jatshokha. Completed
10 Park & Services Construction of children park & welfare centers for officials/labours & Landscaping of colony. Completed
11 Maintenance & Service: R&M of Water Supply facilities for various colonies. Completed
12 Maintenance & Service: R&M of Sanitation & drainage facilities of various colonies. Completed
13 Maintenance & Service: R&M of hospitals (including PHC) Completed
14 Maintenance & Service: Maintenance of Parks, welfare centers, clubs, Lhakhang, auditorium and school. Completed
15 Maintenance & Service: R&M of Rest House and Field Hostels Completed
16 Maintenance & Service: R&M of Research and Quality Control Lab/ Construction material testing and establishment of soil and rock testing laboratory Completed
17 Maintenance & Service: R&M of Colony. On-going works
18 Maintenance & Service: Construction of Crate wall near Dam Sub Station and Repair/Maintenance of Storm Water Drains in PHPA-I Colony. (M/s RMA Construction) On-going works
E R-Communication works
1 Road Improvement Works Construction of Re-aligned National Highway bifurcating at 1.78 Km from Wangdue Bridge for a Stretch of 800m upto the proposed Hesothangkha Bridge at Hesothangkha, Wangdue Phodrang Completed
2 Road Improvement Works Construction of Re-aligned National Highway bifurcating at 1.78km from Wangdue Bridge for a stretch of 850m from RD 830m to RD 1680m Completed
3 Road Improvement Works Construction of Re-aligned National Highway bifurcating at 1.78km from Wandgdue Bridge for a stretch of 1000m from RD 1680m to RD 2680 Completed
4 Road Improvement Works Construction of Re-aligned National Highway bifurcating at 1.78km from Wangdue Bridge for a stretch of 1100m from RD 2680m to RD 3780m Completed
5 Road Improvement Works Construction of Re-aligned National Highway bifurcating at 1.78km from Wangdue Bridge for a stretch of 1045m from RD 3780m to RD 4825m Completed
6 Road Improvement Works Strengthening (Restoration and slope protection works of affected reaches of realigned Wangdue Tsirang National Highway Completed
7 Road Improvement Works Construction of Re-aligned National Highway Bifurcating at 1.78 Km from Rd 3780 Km SH. Construction of Catch Water Drain above National Highway at RD 3940m. Completed
8 Road Improvement Works Improvement of Approach Road & Parking Area for PHPA Head Office at Thimphu. Completed
9 Road Improvement Works Improvement of Primary National Highway (Metsina Wangdue Zam till 19 Km. towards Sungkosh) Completed
10 Road Improvement Works Repair of damaged portion of National Highway from RD 1.78 Km.to RD 7.00 Km. on Wangdue Tsirang highway. Completed
11 Road Improvement Works Improvement of Wangdue-Tsirang Primary National Highway and Wangdue Nobding National Highway. Completed
12 Road Improvement Works Widening of the Wangdue- Tsirang National Highway from Wangdue to Taksha and widening of the Wangdue-Trongsa National Highway till Nobding. Completed
13 Road Improvement Works Widening of Road between Tanalum & Tshimasham on Phuntsholing- Thimphu Highway. Completed
14 Bridge Works Strengthening of Bridges at Damchhu & Simthokha on P/Ling-Thimphu Highway. Completed
15 Bridge Works Improvement of curves at Semtokha fly over. Completed
16 Bridge Works Rehabilitation & Up- gradation of Damchhu & Semtokha Bridge on Phuentsholing- Thimphu highway. Completed
17 Improvement Road Works Regrading of road at Semtokha bridge on Phuentsholing – Thimphu highway. Completed
18 Improvement Road Works Resurfacing & Strengthening of National Highway from Thimphu to Wangdue. Completed
19 Improvement Road Works Construction of Approach Road to STP for PHPA-I Colony. Completed
20 Bridge Works Construction of three nos of bridges to be replaced beyond Gedu to Project site. Completed
21 Bridge Works Design, Fabrication, Transportation, Errection & construction of Steel Truss Bridge (Deck Type) on Hesothangkha stream on the proposed Realigned Wangdue Tsirang National highway at Hesothangkha. Completed
22 R&M works R&M of Road & Bridge works Upcoming works
23 New Road Works Construction of 310m Re-aligned NH from Bjimthangkha BHU towards STP Area. (M/s Nayeab Construction) On-going works
24 Widening Works Widening & Pavement works of Existing Colony from Dam takeoff Jn. to BHU. Upcoming works
25 Widening Works Widening & Blacktopping of Temporary NH Road from BHU to STP PNH Jn. Upcoming works
26 Widening Works Construction of Temporary NH Way from Gaselo Junction to Bjimthangkha BHU. (5 packages) Upcoming works
F P-Maintenance works
1 Building & Other Components Maintenance of K-Buildings (@ 1% of K-Buildings) On-going works
2 Building & Other Components Maintenance of Wangdue-Tsirang Primary National Highway from RD. 9.5 km to RD 20.5 km and maintenance of Hesothangkha Bypass Road on Wangdue-Tsirang Highway from RD 1.74 km to RD 6.5 km Completed