Physical Progress as on 30.04.2021

Contract Packages Cumulative progress (%) as of previous month Cumulative progress (%) as of 30.04. 2021

Physic

MC-1 (including Hydro-Mechanical works) 69.87 69.87
MC-2 (including Hydro-Mechanical works) 100 100
MC-3 (including Hydro-Mechanical works) 98.96 98.75
Electro-Mechanical works 96.36 96.41
Transmission Line 99.94 99.94
Total 87.24 87.22