Physical Progress Report

Physical Progress as of 31 May, 2022

Contract Packages Cumulative progress (%) as of a previous month Cumulative progress (%) as of 30.04.2022

MC-1 (including Hydro-Mechanical works) 69.87 69.87
MC-2 (including Hydro-Mechanical works) 100 100
MC-3 (including Hydro-Mechanical works) 99.21 99.26
Electro-Mechanical works 97.48 97.52
Transmission Line 99.94 99.94
Total 87.45 87.46
Physical progress as of 31st May. 2022